2008 "Cap Logs"

 

2008

Hit Counter from www.statcounter.com

Our Hit Counter




 

The log walls are finely completely up, with cap logs in place. This summer, I had promised my wife that I would spend more time with my family and less time working on the log house then in the past few years. My job requires me to travel a lot, so more time with my 8 and 9 year old, is a good thing. We restarted the walls about August 20th, 2008 from the tenth row and put the cap logs on the 20th row. Our second logger never came through with the rest of the roof rafters for us. We have since hired another logger to supply us with hemlock rafters at a good price for delivery this winter. We did what we could and will restart the RPSL, Ridge pole, rafters, roof windows, doors, floors, and chinking in the spring and summer of "2009".